Scope of work
Precast construction of 14 portal crossheads offsite.
Construction of 38 piers in under 60 days.
Installation & grouting of 30 precast headstocks.
Insitu stitch pours of 76 spans of U-Troughs.
North Abutment FRP construction.
Precast construction of 14 portal crossheads offsite.
Construction of 38 piers in under 60 days.
Installation & grouting of 30 precast headstocks.
Insitu stitch pours of 76 spans of U-Troughs.
North Abutment FRP construction.