Caulfield to Dandenong Level Crossing Removal

PROJECT DETAILS

Our Client: LLECPB Crossing Removal JV

End Client: Level Crossing Removal

Completed: 2017-2018

Equipment: Manitou 4T, 25T Superlift Franna, 40T Crawler Crane, EWP, Scissor lift

Scope of work

The first stage of this project was the construction of 9 Piers and 3 Abutments, including the fabrication and installation of formwork, installation of reinforcement, casting and finishing concrete.

The second stage of the project was the construction of the Retaining Walls combined into different structures: 428 linear meters of slabs and stitch pours, erection and placement of 160 precast panels, 5 Pedestals, 60 linear meters of transition, approach slabs and derailment kerbs. The works consisted of: craneage and propping of precast panels, fabrication and installation of formwork and falsework, installation of reinforcement, casting, grouting and finishing concrete.